Timeline

NOTE: Customer involvement is encouraged throughout the entire process. Scheduled appointments with the Builder are required.

0 – 1 MONTH

  • Site visit with Buyer to discuss layout
  • Buyer chooses structural options
  • Apply for a building permit
  • Clear lot
  • Strip topsoil
  • Install all required silt fencing & environmental protection units.
  • Excavate
  • Order windows and exterior doors
  • Pour Footings and concrete walls
  • Start Framing

1 – 2 MONTHS

  • Home Customizer appt to choose exterior selections
    Finalize all exterior selections ________
  • Finish rough framing
    Field measure for stairs Homeowner framing walk through
  • Install asphalt roof
  • Install windows and exterior doors
    Selections meeting for interiors scheduled ________
    Finalize all cabinetry selections________
    Finalize all flooring selections________
    Finalize all plumbing selections________
  • Install finish stairs
  • Pour basement floor and garage floor
  • Rough in HVAC
  • Meet electrician for a walkthrough. Scheduled ________
  • Filed measure for trim. Scheduled ________

2 – 3 MONTHS

  • Install siding
  • Install front concrete pad and walk
  • Install rear concrete pad
  • Rough in plumbing
  • Install cultured stone for exterior fireplace
  • Rough in electrical

3 – 4 MONTHS

  • Install 1000 gallon underground propane tank
  • Install water and sewer lines
  • Dig trench and rough in utilities (electric, phone, cable)
  • Insulate exterior walls
  • Install fireplace
  • Drywall and three coat tape interior
  • Install bath vanities and tops
  • Customer walkthrough

4 – 5 MONTHS

  • Install interior doors and millwork
  • Paint Interior
  • Tile bathrooms
  • Install driveway
  • Paint exterior
  • Install kitchen cabinets
  • Install prefinished oak flooring in the foyer
  • Customer Millwork walkthrough

5 – 6 MONTHS

  • Install kitchen appliances
  • Install Corian countertops
  • Finish heating and air conditioning
  • Finish plumbing
  • Finish electrical
  • Install bathroom mirrors and shower doors

6+ MONTHS

  • Paint and touch up walls and trim
  • Install carpet
  • Final cleaning of baths, floors and windows
  • Final grading and landscaping
  • Pre-Settlement walkthrough
  • Settlement
  • Post settlement – homeowner moves in!
  • 1 year warranty