Timeline
NOTE: Customer involvement is encouraged throughout the entire process. Scheduled appointments with the Builder are required.
0 – 1 MONTH
- Site visit with Buyer to discuss layout
- Buyer chooses structural options
- Apply for a building permit
- Clear lot
- Strip topsoil
- Install all required silt fencing & environmental protection units.
- Excavate
- Order windows and exterior doors
- Pour Footings and concrete walls
- Start Framing
1 – 2 MONTHS
- Home Customizer appt to choose exterior selections
Finalize all exterior selections ________ - Finish rough framing
Field measure for stairs Homeowner framing walk through - Install asphalt roof
- Install windows and exterior doors
Selections meeting for interiors scheduled ________
Finalize all cabinetry selections________
Finalize all flooring selections________
Finalize all plumbing selections________ - Install finish stairs
- Pour basement floor and garage floor
- Rough in HVAC
- Meet electrician for a walkthrough. Scheduled ________
- Filed measure for trim. Scheduled ________
2 – 3 MONTHS
- Install siding
- Install front concrete pad and walk
- Install rear concrete pad
- Rough in plumbing
- Install cultured stone for exterior fireplace
- Rough in electrical
3 – 4 MONTHS
- Install 1000 gallon underground propane tank
- Install water and sewer lines
- Dig trench and rough in utilities (electric, phone, cable)
- Insulate exterior walls
- Install fireplace
- Drywall and three coat tape interior
- Install bath vanities and tops
- Customer walkthrough
4 – 5 MONTHS
- Install interior doors and millwork
- Paint Interior
- Tile bathrooms
- Install driveway
- Paint exterior
- Install kitchen cabinets
- Install prefinished oak flooring in the foyer
- Customer Millwork walkthrough
5 – 6 MONTHS
- Install kitchen appliances
- Install Corian countertops
- Finish heating and air conditioning
- Finish plumbing
- Finish electrical
- Install bathroom mirrors and shower doors
6+ MONTHS
- Paint and touch up walls and trim
- Install carpet
- Final cleaning of baths, floors and windows
- Final grading and landscaping
- Pre-Settlement walkthrough
- Settlement
- Post settlement – homeowner moves in!
- 1 year warranty